Summary of PennDOT projects

Body


  1. Harvey Avenue Bridge---Construction began June 5th. The detour route consists of utilizing Butterlane in one direction and utilizing Harvey Avenue to Carsonia Avenue and Butterlane to St. Lawrence Avenue. The project should be completed mid-August.
  2. Gibraltar Road Bridge---Construction began the end of May and will be completed by early October of this year. The detour route consists of utilizing SR 724 to I-176 to SR 422 (Perkiomen Avenue).
  3. East Neversink Road Bridge----Deck repairs are complete….structural work is being completed to the superstructure along SR 422….no detour route; except for flagging as required on SR 422.
  4. Perkiomen Avenue---Scheduled to begin on June 18th with redirection of travel lanes at night time. Four lanes of traffic (two in each direction) will be maintained throughout the duration of the project; except for flagging as required. The south lane will be closed to accommodate utility work, curbing, ADA ramps and full depth reconstruction. The remaining sections will be completed in 2019. The total project is to be completed by October of 2019.
  5. Shelbourne Road----Construction to commence the week of June 18th . The detour route consists of Gibraltar Road to SR 422. The project is scheduled to be complete by mid-August.
  6. SR 562 Bridge----scheduled to be let in April 2019. No detour plan has been presented to the Township.
  7. Oley Turnpike Road Bridge---Project is located in St. Lawrence Borough; however, the decking will be replaced during July through August 2018. Detour route consists of SR 562 to Oley Turnpike Road. The Oley Turnpike resurfacing project will be complete in June of 2018. 
More information will be provided as available. Thank you.